Princess Alexandra Hospital – Day Surgery

Location:

Woolloongabba, QLD

Client:

Queensland Health

Duration:

3 months
Back to Projects

This project involved the complete upgrade of air conditioning system and ventilation systems serving the operating theatres. The project included:

Decommissioning and removal of existing air conditioning systems. 

Supply and installation of new air handling units, HEPA filtration, humidifiers, ductwork, etc.

Upgrade of Mechanical Switchboards and controls to operate the above plant and equipment.

Supply and installation of centralised BMS controls to operate the above plant and other services.

Coordination with Queensland Health. Works carried out within an operational Day Surgery.

NEBB Certified Commissioning of the completed systems.